HIGHLIGHTS (all amounts are in A$ unless otherwise stated)
• Initial production target of ~24koz @ 8.3g/t Au is a 24% increase in ounces from the previous
study. The Star of Mangaroon remains open along strike and at depth. As such, the initial
production target is subject to expansion from extensional drilling.
• No change needed to the previous pit design with the majority of extra ounces contained
within the envelope and closer to surface.
• Max cash drawdown reduced from $10.2M to ~$5.4M.
• Robust financials at $5,500oz include:
➢ Maximum cash drawdown of ~$5.4M
➢ All-in Sustaining Cost (“AISC”) of $2,020/oz
➢ Operating Cashflow after all Capital and Tax (“Operating Cashflow”) of ~$78.2M
➢ 99% Measured and Indicated Resource
• Mining approvals submitted, all leases granted, updated contractor quotes incorporated and
agreements advancing to move into production.
Dreadnought Resources Limited (“Dreadnought”) is pleased to announce the scoping study
update for an initial open pit at Star of Mangaroon, part of the 100% owned Mangaroon Gold
Project, located in the Gascoyne region of Western Australia.
Dreadnought’s Managing Director, Dean Tuck, commented: “The updated scoping study for Star of Mangaroon
highlights the impact of additional high grade, near surface mineralisation at the Star of Mangaroon with reduced max
cash drawdown and additional processed ounces and of course the increased gold price.
With the scoping study delivered, Dreadnought will look to bring discussions with third parties to outsource funding,
development, haulage & processing to a conclusion as quickly as possible. The cashflow from this operation would
present a major milestone for Dreadnought and our shareholders as the proceeds could be used to fund future
exploration and potentially return capital to our shareholders.
The improved financial outcome of the updated scoping study has justified the additional work over the past year
undertaken by the Dreadnought Team. With gold prices continuing to climb, there could be no better time to bring a
high-grade gold asset into production.
In parallel with our efforts to get the Star of Mangaroon into production, we continue to pursue opportunities to add
resource ounces on our granted mining leases with an aim to extend production and operations. We see potential to
extend the Star of Mangaroon along strike and at depth.
For the medium and long term, our team continues to drill compelling targets that result from our ongoing target
generation and definition work both at Mangaroon and Illaara with the aim of delivering a major gold discovery.
We believe that Dreadnought is now well positioned to take advantage of its gold opportunities while still providing
significant leverage and optionality for our shareholders with our critical metal and base metal assets also at
Mangaroon. We look forward to the remainder of 2025 and to 2026 as we deliver on our more gold faster strategy.”
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 2
Cautionary Statement as Required by JORC/ASX – Scoping Study
The October 2025 Scoping Study (“the Study”) has been prepared to ascertain whether a business case can be made
before proceeding with more definitive studies of Star of Mangaroon’s viability. The Study is a preliminary technical and
economic assessment of the potential viability of Star of Mangaroon.
The Study is based on low level technical and economic assessments that are not yet sufficient to support the estimation of
Ore Reserves. Further exploration and evaluation work and appropriate studies may be required before any estimate of Ore
Reserves or to provide any assurance of an economic development case.
The Study includes a production target comprising Measured (77%), Indicated Resources (23%), and Inferred (<1%).
Investors are cautioned that the Study is at a scoping study level of confidence. Further study work is required to develop all
project modifying factors including but not limited to mining dilution, ore loss, metallurgical recoveries, geotechnical analysis,
cost estimates, environmental and social impacts.
The Study is based on the material assumptions outlined in this announcement including assumptions about the availability
of funding. While Dreadnought considers all the material assumptions to be based on reasonable grounds, there is no
certainty that they will prove to be correct or that the range of outcomes indicated by the Study will be achieved.
To achieve the range of outcomes indicated in the Study, funding in the order of $5.4M (maximum cash drawdown) will
likely be required. Investors should note that there is no certainty that Dreadnought will be able to raise that amount of
funding when needed. It is also possible that such funding may only be available on terms that may be dilutive to or otherwise
affect the value of Dreadnought’s existing shares.
It is also possible that Dreadnought could pursue other ‘value realisation’ strategies such as a sale, partial sale or joint
venture of Star of Mangaroon or its other projects. If it does, this could materially reduce Dreadnought’s proportionate
ownership of or share of Operating Cashflow from the relevant project(s).
Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the Study.
This announcement has been prepared in compliance with the JORC Code 2012 Edition (“JORC”) and the ASX Listing
Rules. All material assumptions, on which the forecast financial information is based, have been included in this
announcement and are also outlined in the attached JORC Table disclosures.
Overview
The Jan 2025 Study (“Jan Study”), (ASX 25 Jan 2025) has been updated due to: additional drilling; increased
Resource (ASX 24 Sep 2025); firming up of cost inputs and changes to recoveries and gold price. Specifically, the
material changes include:
• Increased Resource from 23,300 to 27,000 ounces
• Updated haulage costs based on contractor quotes and likely road train arrangements
• Updated road maintenance allowances for Shire roads
• Updated mining contractor and mine management / technical services costs
• Conservative metallurgical recovery assumption of 96%
• Updated gold price. Pit optimisations completed at $5,000/oz with financials presented at $5,500/oz and spot
($6,000/oz)
Other aspects of the Jan Study are materially as previously released, with the optimisation and mine scheduling
following the same approach, parameters, philosophy and proposed equipment.
Physical & Financial Summary
The Study demonstrates substantially improved economics and produces ~24koz generating an Operating
Cashflow of ~$78.2M (@ $5,500/oz) over one year at an AISC of $2,020/oz.
A gold price of $5,500/oz has been used in the Study. The gold sector is strong with the average spot price since
October 2024 consistently above $5,500/oz. Indicative forward market prices available are at ~$6,400oz.1
1
Average gold forward sales price based on a $6,411/oz spot price and assumes commencing delivery date of September 2026 for 12 months. The
forward prices have been provided by an independent source (a large Australian bank) with inputs used being the prevailing data as of 27 October
2025. The quoted price of $6,400/oz has been rounded down to the nearest $10.
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 3
Table 1: Star of Mangaroon Physicals Summary
Project Physicals Units Total Jan Total Oct % Diff
Duration Months 12 12 0%
Mined Ore kt 62.1 92.9 50%
Grade g/t Au 10.0 8.3 -17%
Gold in Ore koz 19.9 24.7 24%
Recovery % 98 96 0%
Gold Recovered koz 19.5 23.8 22%
Table 2: Star of Mangaroon Financial Summary
Project Financials Units Total Jan Total Oct %Diff
Gold Price $/oz 4,100 5,500 34%
Revenue $M 80.1 131.0 64%
Capital Costs
Pre-Production Infrastructure $M 1.7 1.7 0%
Pre-Production Development $M 1.2 1.2 0%
Rehabilitation $M 1.8 1.8 0%
Operating Costs
Mining $M 25.5 26.7 5%
Ore Haulage and Processing $M 6.7 16.3 143%
Royalties $M 3.0 5.1 70%
Operating Cashflow (after all Capital and Tax) $M 40.1 78.2 95%
Maximum Cash Drawdown $M 10.2 5.4 -47%
AISC $/oz 1,800 2,020 12%
Investors are advised the Study is a preliminary economic assessment based on assumptions outlined in this
document and a range of financial outcomes are possible: +/-10% variance from the base case is shown below.
A gold price movement of $100/oz changes Operating Cashflow by ~$2.3M as shown in the price range below:
Table 3: Sensitivity to $100/oz gold price increments
Gold Price $/oz Operating Cashflow ($M)
$5,000 $66.8
$5,100 $69.1
$5,200 $71.3
$5,300 $73.6
$5,400 $75.9
$5,500 (Base Case) $78.2
$5,600 $80.5
$5,700 $82.8
$5,800 $85.1
$5,900 $87.4
$6,000 (Current) $89.7
$6,100 $91.9
$6,200 $94.2
$6,300 $96.5
$6,400 (Forward 27/10/20025) $98.8
$6,500 $101.1
Opportunities
There are extensive opportunities to build on the Study including:
• Potentially proving up additional Resources on existing mining leases, these include Popeye, Star of Mangaroon
extensions, Two Peaks, Lead Gold Mine and Pritchard’s Well.
• Potential for gold recovery from an existing heap leach located on the Star of Mangaroon mining lease and
within the limits of the pit design.
• Potential for underground mining. Deeper drilling and an open pit to underground transition study will
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 4
evaluate the potential for an underground mine following the open pit.
• Spare capacity within the mining fleet may be utilised for additional mining within the operational period.
• Use of forwards increases the Study Operating Cashflow by ~$20M over base case.
Existing Mining Leases
There are currently 5 granted mining leases within the area covering historical mines and include the Star of
Mangaroon, Lead Gold Mine, Two Peaks and Pritchard’s Well. Proving up additional Resources on the existing
mining leases could extend production with minimal additional approvals.
Drilling is ongoing at Pritchard’s Well.
Figure 1: Long Section of the Star of Mangaroon showing the location of historic, recent and planned drilling relative to the
approximate location of the Star of Mangaroon pit outline.
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 5
Camp Scale Prospects
Dreadnought has identified six camp scale prospects with the potential to deliver additional discoveries. These
include Bordah, High Range North, High Range South, Alma Intrusion, Minga Bar and additional targets around the
Star of Mangaroon. Any significant discovery could provide material to extend operations.
With all camp scale prospect stream sediment work complete, work focuses on target generation and definition
soil sampling deliver targets for drilling in 2026.
Figure 2: Plan view image of a portion of Mangaroon highlighting the main gold and base metal camp scale prospects,
and recently collected stream sediment samples, which are the focus of ongoing target generation and definition work.
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 6
JORC Code 2012 and ASX Listing Rules Requirements
This announcement has been prepared in accordance with JORC and ASX Listing Rules. Investors are referred to
several important statements in relation to this announcement and the Study contained herein including the
Cautionary Statement; Forward Looking Statements; Sensitivity Analysis; and Competent Persons’ Statements.
Cautionary Statement as Required by Clause 38 of JORC
Margin for Error: The Study documented in this announcement has a +/-30% Scoping Study level of accuracy.
Assumptions: The Study is based on the material assumptions outlined in this announcement. While Dreadnought
considers all the material assumptions to be based on reasonable grounds, there is no certainty that they will prove
to be correct or that the range of outcomes indicated by the Study will be achieved.
Further Work Required: The Study has been undertaken to determine the potential viability of open pit mining
at Star of Mangaroon. Scoping studies are preliminary technical and economic assessments of the potential viability
of mining and are based on low level technical assessments that are not yet sufficient to support the estimation of
Ore Reserves. Further exploration and evaluation work and appropriate studies may be required before the
estimation of Ore Reserves or to provide any assurance of an economic development case.
Value Realisation: Dreadnought could pursue other ‘value realisation’ strategies such as a sale, partial sale or
joint venture of Star of Mangaroon. If it does, this could materially reduce Dreadnought’s proportionate ownership
of or Operating Cashflow from the relevant project(s).
Uncertainty: Given the uncertainties involved, investors should not make any investment decision based solely
on the results of the Study.
Economic Viability: Dreadnought considers the deposits subject to the Study to be economically viable based
on a gold price of $5,500/oz.
Funding: To achieve the range of outcomes indicated in the Study, funding of ~$5.4M (maximum cash drawdown)
will be required to commence initial production. This funding is assumed. Investors should note that there is no
certainty that Dreadnought will be able to generate or raise that amount of funding when needed. It is also possible
that such funding may only be available on terms that may be dilutive to or otherwise affect the value of
Dreadnought’s existing shares.
The Company believes that it is reasonable to assume there will be available funding to commence Star of
Mangaroon because:
• The outcome of the Study provides an attractive return on capital investment and generate a robust cashflow
at a range of gold prices below current market levels. This provides a strong platform to attract both debt
and equity investment.
• The board and management of have a strong track record of raising debt/equity funding as required fund
development.
• At 30 September 2025 Dreadnought had ~$24M in cash after allowing for a capital raising undertaken in early
October 2025.
• The project is in a
stable geopolitical
environment with
established
infrastructure and
regulations. Details
of the Study follow.
Figure 3: Photo of the
historical infrastructure at
the Star of Mangaroon.
STAR OF
MANGAROON
SCOPING STUDY UPDATE
October 2025
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 8
1. INTRODUCTION
Dreadnought owns 100% of ~5,300km2
of highly prospective ground at Mangaroon located ~250km south-east of
Exmouth in the Gascoyne Region of WA and is accessed by the Towera, Lyndon and Ullawarra Roads.
Part of the area is comprised of the ~10km x 15km Mangaroon Gold Camp (Au, Cu-Zn-Ag-Au): where fractured,
small-scale ownership has limited previous gold exploration with only ~200m of the >12km long Mangaroon Shear
Zone having been drilled. This area is a focus for Dreadnought.
The Star of Mangaroon, located within the Mangaroon Gold Camp, was mined between 1960 and 1983 and produced
a total of 7,464 oz @ 34.8 g/t Au.
Dreadnought’s objective is to commence open pit mining at Star of Mangaroon and to process material at Black Cat’s
Paulsens processing facility. Ongoing exploration is expected to prove up further gold in the region for future mining.
Figure 4: Star of Mangaroon location relative to Paulsens processing facility.
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 9
2. STUDY PARAMETERS
The Study is based on the following outsourced activities:
• Constructing a mobile camp proximal to the mine;
• Clearing vegetation and removal of topsoil prior to mining;
• Contractor open pit mining for ~12 months;
• Contract haulage;
• Processing at Black Cat’s Paulsens processing facility; and
• Contractor demobilisation at the completion of mining.
3. STUDY TEAM
The following consultants contributed to the Study.
Table 4: Consultant contributions to the Study
Study Area Consultant Scope
Fauna & Flora Onshore Environmental
• Desktop flora, vegetation & fauna
assessment (2021)
• Reconnaissance flora and vertebrate fauna
survey (2021)
• Targeted flora survey & vegetation type
mapping (2022, 2023)
• Fauna survey (2023)
Geotechnical Peter O’Bryan & Associates • Pit wall stability assessment (2024)
Metallurgy Strategic Metallurgy
• Gravity and cyanide leachable recovery of 5x
diamond core composite samples (2024)
Mineral Resource (Original,
2024)
Payne Geological Services
• Validation of exploration drilling data
• Interpretation and modelling of all geological
domains and structures
• Generation of a Resource model (2024)
Mineral Resource Update
(September 2025)
Ashmore Advisory
• Validation of exploration drilling data
• Interpretation and modelling of all geological
domains and structures
• Generation of a Resource model (2025)
Mine Planning (Scoping
Update)
MineBuild Global
• Open pit optimisation and mine scheduling
based on the Jan Study pit design
• Cost model update based on Jan Study cost
model
4. PERMITS & APPROVALS
Star of Mangaroon has low approval barriers being located on approved and developed mining lease (M09/175) and
is accessible via miscellaneous lease L09/116 and L09/115.
Baseline environmental studies required to support a Mining Proposal submission have been completed and submitted:
Table 5: Studies completed
Study Area Consultant Scope
Fauna & Flora Onshore Environmental • Targeted fauna survey
Geotechnical Peter O’Bryan & Associates
• Waste dump final slope stability assessment
• Abandonment bund position
Hydrology/ hydrogeology Pennington Scott
• Groundwater to support operations
• Flooding assessment
Soil Characterisation Botanica Consulting
• Soil reclamation strategy
• Waste dump final slope stability assessment
Waste Rock Characterisation Botanica Consulting • Acid mine drainage & rehabilitation
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 10
5. GEOLOGY & MINERALISATION
Star of Mangaroon lies within the Proterozoic Gascoyne Province, in a zone of highly strained NW trending paragneiss
and paraschistose metamorphic rocks whose protolith were either sedimentary or felsic volcanic rocks. The gneiss
outcropping at Star of Mangaroon is a laminated sugary quartz micaceous (biotite) rock which has undergone upper
amphibolite to granulite facies regional metamorphism.
The principal gold-bearing horizon consists of an anastomosing quartz vein with a strike of ~10° dipping to the east
at ~65°. The gold-bearing vein system is about 150m long and 2-4m wide, hosted in a NS trending foliation. The
mineralisation in the northern portion appears to change to a more stockwork type of disseminated gold, and changes
to a more NW trending direction as it becomes sub-parallel to the WNW-ESE trending regional structural. Based
on analysis of hand specimens and historical mineralogy reports, the mineralisation at Star of Mangaroon is hosted in
crystallised quartz vein, consisting of a quartz-muscovite-pyrrhotite-chalcopyrite-arsenopyrite gold assemblage.
Geochemical pathfinders for the gold mineralisation observable in orientation soil surveys and whole rock
geochemistry include Te, Sb, Bi, & As, as well as elevated Ag, Cu, and Pb.
5.1 Resource Model
The September 2025 Resource model was used for the Study. The Resource is ~99% Measured and Indicated.
Table 6: Star of Mangaroon September 2025 Resource (2g/t Au cut-off grade)
Type
Measured Indicated Inferred Total
Tonnes Au (g/t) Au (Oz) Tonnes Au (g/t) Au (Oz) Tonnes Au (g/t) Au (Oz) Tonnes Au (g/t) Au (Oz)
Surface 8,300 1.0 300 8,300 1.0 300
Transition 6,300 24.9 5,100 3,300 6.5 700 9,600 18.6 5,800
Fresh 33,200 13.5 14,400 23,500 8.5 6,400 1,000 5.1 200 57,700 11.3 21,000
Total 39,500 15.3 19,400 26,800 8.2 7,100 9,300 1.4 400 75,600 11.1 27,000
6. GEOTECHNICAL PARAMETERS
Recommendations for wall design were based on information from geotechnical logging of two geotechnical diamond
drill holes (SOMDD007, SOMDD009) and an additional six diamond drill holes (SOMDD001 – SOMDD006) from
within the open pit. The base case wall design parameters are as follows:
Table 7: Open pit wall design parameters
Parameter
North & West
Walls
South & East
Walls
Upper Limit
(mRL)
Lower Limit
(mRL)
Face Height (m) 10 10 Surface 275
Face Height (m) 20 20 275 235
Face Height (m) 30 30 275 Base of pit
Face Angle (°) 55 50 Surface 275
Face Angle (°) 60 55 275 255
Face Angle (°) 75 60 255 235
Face Angle (°) 75 75 235 Base of pit
Berm Width (m) 5 5 275 275
Berm Width (m) 7 7 255 Base of pit
7. HYDROLOGY AND HYDROGEOLOGY
The region comprises low undulating hilly country with stony and hardpan wash plains. Minor local drainage channels
intersect the area which are subject to seasonal flow. Natural groundwater level in the region is 20-30m below surface.
Groundwater is fresh to brackish, ranging from 1,000-5,000ppm TDS.
Groundwater inflow rates below the water table are expected to be minimal (<2.5L/sec). This is interpreted from
water return from drilling and an assessment of data from existing bores within a 5km radius of Star of Mangaroon.
To manage flooding, all landforms and work areas have been designed away from watercourses.
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 11
8. METALLURGICAL TEST WORK
Metallurgical test work comprised conventional gravity and carbon-in-leach gold recovery at a range of grind sizes
and used site water used at the Paulsens processing facility in four of the five tests2
.
Composite samples from the 2023 Star of Mangaroon RC drilling program (SOMRC004-SOMRC008) were selected
to represent a range of head grades and locations within the mineralised lode and inside the open pit.
Gravity tests were carried out to simulate a gravity recovery stage as part of a conventional milling circuit. To
approximate this, the sample was stage ground to 212µm using a laboratory rod mill and the product was upgraded
using a Falcon concentrator. The concentrate was then leached and the solution analysed for gold content. The gravity
tailings were then homogenised with the bulk sample before cyanidation test work.
Cyanide leach tests were carried out at P80 grind sizes of 212µm, 150µm, 106µm, 75µm. Milled samples were
transferred to a bottle where cyanide and lime were added to achieve the required pH of 10.
The combined gravity and leach extractions and associated reagent consumptions are shown in Table 8.
Table 8: Gravity and leach test results for composites S1 – S5
Comp.
ID
Grind
Size
(μm)
Head
Grade
(g/t)
Gravity
Gold
Recovery
(%)
Gold Extraction (%) Tails
Grade
(g/t)
Reagent
Consumption
4 hrs 8 hrs 24 hrs 48 hrs
NaCN
(kg/t)
Lime
(kg/t)
S1
212
5.91 55.6
87.6 88.9 91.1 91.1 0.53 0.30 1.44
150 92.3 94.0 95.1 95.1 0.29 0.33 1.33
106 96.4 96.4 96.4 96.4 0.21 0.34 1.83
75 97.1 97.1 97.4 97.4 0.15 0.31 2.10
S2
212
15.5 85.2
94.0 96.4 97.4 97.4 0.40 0.25 0.21
150 97.5 98.3 98.3 98.3 0.26 0.15 0.31
106 98.1 99.3 99.4 99.4 0.09 0.08 0.35
75 99.0 99.5 99.5 99.5 0.08 0.18 0.43
S3
212
6.57 76.0
76.5 78.5 79.1 79.1 1.37 0.53 1.43
150 92.9 95.3 95.3 96.0 0.26 0.37 1.43
106 95.6 98.0 98.6 98.6 0.09 0.30 1.26
75 98.1 98.7 98.7 98.7 0.09 0.58 1.33
S4
212
22.5 84.6
90.3 92.7 95.7 96.8 0.72 0.65 1.71
150 92.0 94.7 97.7 98.9 0.25 0.90 1.67
106 92.2 94.1 97.5 98.3 0.38 0.66 1.66
75 93.0 95.0 98.7 98.8 0.27 0.66 1.98
S5
212
4.59 70.4
94.5 96.2 97.9 98.2 0.08 0.34 1.50
150 94.0 95.7 98.3 98.3 0.08 0.33 1.15
106 95.5 97.1 98.3 98.3 0.08 0.23 1.17
75 95.6 97.2 98.4 98.4 0.07 0.33 1.27
Average 11.01 74.4 93.6 95.2 96.4 96.7 0.39 1.28
Gravity recoveries range from 55-85% with an average gravity recovery of 74% using a coarse grind size of 212µm.
The highest recoveries were recorded in composites S2 and S4, however all results are well above industry averages
and reflect the high-grade (coarse gold) nature of these samples.
Table 9: Summary table of metallurgical recovery and reagent usage
Composite ID 106µm 24hr Recovery 75µm 24hr Recovery
S1 96.4% 97.4%
S2 99.4% 99.5%
S3 98.6% 98.7%
S4 98.3% 98.8%
S5 98.3% 98.4%
Average 98.2% 98.6%
Estimated Solution and Carbon Attrition Losses 0.02g/t 0.02g/t
Gold Recovery (incl. solution and carbon losses) 98.0% 98.3%
A conservative metallurgical recovery of 96% was selected for the Study update financials following discussions with
Black Cat and operational variability.
2
ASX announcement 14 October 2024: Exceptional Gold Recoveries from Star of Mangaroon – Mangaroon Au (100%).
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 12
9. OPEN PIT DESIGN – MODIFYING PARAMETERS
MineBuild was engaged to replicate the pit optimisation methodology used in the initial the Jan Study but based on
the September 2025 Resource. The process involved:
• Preparing a diluted model by applying dilution skin, comparable to the approach used previously.
• Updating pit optimisation input parameters to align with recent pricing.
The revenue factor (RF) 1.0 pit shell generated was comparable to the pit design developed during for the Jan Study
and hence was retained.
A revised mining schedule was prepared, with the resultant mining physicals schedule used to update the cost and
cashflow models.
9.1 Resource Dilution
The Resource block model was coded with a dilution skin using Deswik software, as described in Table 10 below.
Table 10: Resource model dilution settings
Parameter Units Setting
Cut-off Grade g/t Au 1.0
Minimum Ore Width (excl. dilution) M 1.0
Dilution Skin Width M Footwall = 0.5
Hangingwall = 0.5
Minimum Waste Pillar M 2.0
Other Block Dimensions M Y = 5.0
Z = 2.5
9.2 Open Pit Optimisation
Open pit optimisation shells were generated using the pseudoflow function in Deswik software using the diluted
block model, contractor supplied rates, recommended overall slope angles (as per geotechnical assessment) and
metallurgical recovery.
Table 11: Open pit optimisation parameters
Parameter Units Unit Rate
Gold Price $/oz $5,000
Royalties (State and other) % Revenue 4%
Overheads $/bcm $10.11
Drill and Blast $/bcm Transitional = $2.54
Fresh= $3.98
Load and Haul Waste (average) $/bcm $8.8
Load and Haul Ore (average) $/bcm $10.1
Ore Haulage $/t $142.5
Processing $/t $55.00
Mining Recovery % 95%3
Metallurgical Recovery % 98%
Slope Angles ° Transitional = 40°
Fresh = 45°
9.3 Open Pit Mine Design
There was no material spatial variance between this Study’s optimised open pit shell and the previous open pit design.
As such, the Jan Study pit design was adopted for this Study.
Open pit design parameters included:
• 12m wide, 1:9 gradient single lane ramp for the entirety of the open pit:
• 20m vertical interval between dual lane passing bays; and
• Open pit walls and berms were designed according to the specified geotechnical parameters detailed in Table 7.
The pit design is 250m long, 180m wide and 85m deep and is shown in Figures 5-7.
3
95% mining recovery was applied to the optimization process. The open pit physicals apply 100% mining recovery, with an additional 200% dilution
applied to the 5% Ore excluded from the optimization process.
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 13
Figure 5 (above): Long section (looking west) of the Star of
Mangaroon open pit design and Resource
Figure 6 (right): Oblique view of the Star of Mangaroon open pit
design and Resource
Figure 7: Star of Mangaroon open pit mine infrastructure on mining lease M09/175.
Unit 1, 4 Burgay Court,
Osborne Park, WA 6017
+61 8 9473 8345
info@dreres.com.au
www.dreadnoughtresources.com.au
ASX:DRE Dreadnought Resources Ltd 14
Other infrastructure designed on tenement M09/175 include: a waste dump, ore pad (“ROM”), water storage dam,
topsoil storage stockpiles, roads, etc. Quantities for clearing, stripping, and stockpiling of vegetation and topsoil were
calculated using the design footprint.
Other mine design and scheduling assumptions include the following:
• Required RC grade control drill metres for the life of mine were estimated to be 1,500m.
• Blast hole drill metres and explosive quantities were calculated using the parameters detailed in Table 12. 100%
blasting was assumed.
• Load and haul production was scheduled based on the capability of a 100t class excavator and 100t rigid trucks,
mining 2.5m flitch heights, with consideration of haulage distance to stockpile locations.
Table 12: Open pit drill and blast parameters
Production Drilling Parameters
Material Type Transitional Fresh
Hole Diameter (mm) 102 102
Burden (m) 3.0 2.7
Spacing (m) 3.4 3.1
Sub-drill (m) 0.5 0.7
Wall Control Factor (batter holes/pre-splits) 1.05 1.17
Powder Factor (kg/bcm) 0.5 0.7
Ave Penetration Rate (m/hr) 30 22
9.4 Mining Recovery
The Study assumes 100% of the diluted Resource is recovered as Ore, with the following assumptions:
• 95% of the Ore mined as per the diluted Resource with no further modifying factors applied; and
• 5% of the Ore applies a nominal 200% additional dilution a